Case 01
The deviation was corrected with the silo still at the factory
At this agri-food process manufacturer, it was confirmed that the new silo fitted the existing concrete base before a crane was moved, with production running.
Agri-food process manufacturerReplacement of two silos on the existing concrete base
What was happening
An agri-food process manufacturer had to replace two large silos on the concrete ring of the old ones, with production running and unreliable as-built drawings of the base.
What we did
A3D laser-scanned the real condition, built the as-built BIM model of the base and inserted the new silo into the model to check the fit before a crane moved.
What changed
The model uncovered a deviation that no drawing showed, weeks before the crane reached site: it was corrected on the drawings, with the silo still at the factory.